Nghiên cúu các nguyên nhân gây sự cố khi thi công công trình ngầm bằng máy đào hẩm loại nhỏ

- Authors: Dang Trung Thanh
Affiliations:
Hanoi University of Mining and Geology
- Keywords: Tunnel digging machine, breakdown, jacking pipe, working face, instability
- Received: 15th-Nov-2015
- Online: 30th-June-2016
- Section: Mineral Beneficiation and Processing
Abstract:
Disturbance in micro tunneling projects is a complex multivariate problem. Disturbance leads to delay time in micro tunneling. Delay time increases the project duration and consequently the project cost. The paper presents the main causes leads to nonworking time of a micro tunneling. The information will supply useful informations for manager, designer and contractor who works in related fields in Vietnam in the near future.

1. French Society for Trenchless Technoíogy. Microtunneling and Horizonta. Drilling: Recommendations. John VViley & Sons, 2004.
2. Mohamed, Y. H. and R. s. Gary (2007). Delay time anaíysis in microtunneiing projects. Journal of Construction Engineering and Management 133(2), 191-195.
3. stein, D. (2005). Practical Guideline for the Application of Microtunneiling Methods. Bochum, Germany. ISBN: 3-9810648-0-1.