Nghiên cứu xác định thời gian thi công công trình ngầm bằng máy đào hẩm loại nhỏ có xét ảnh hưởng của sự cố

https://mij.hoimovietnam.vn/en/archives?article=16064
  • Affiliations:

    Hanoi University of Mining and Geology

  • Received: 8th-Nov-2015
  • Accepted: 12th-Oct-2016
  • Online: 31st-Dec-2016
Pages: 25 - 28
Views: 36
Downloads: 1
Rating: , Total rating: 0
Yours rating

Abstract:

In last 20 years, there are more than 1000 Micro Tunnel Boring Machines (MTBM) has been used for tunnel constructions with small crosssection. There are a lot of projects used MTBM’s frequently do not reach their targeted production performance. Reasons can be technical failures, insufficient capacity dimensioning, organizational deficiencies, or sensitive supply chains, some technical problems is occurred in the process of construction. One year in order to fix the disturbances at project in Nhiêu Lộc-Thị Nghè canal is a typical example. The time to finsh the project is important information that investors as well as contractor need to make the decisions during construction process, Therefore, the MiSAS module combined with the empirical formula is used in the paper for predicting the construction time of tunnel with MTBM considering the effects of the disturbances. Moreover, two actual projects at the city of Recklinghausen, Germany, is used for the study case.

How to Cite
Thanh, D.Trung 2016. Nghiên cứu xác định thời gian thi công công trình ngầm bằng máy đào hẩm loại nhỏ có xét ảnh hưởng của sự cố (in Vietnamese). Mining Industry Journal. XXX, 6 (Dec, 2016), 25-28. .
References

1. Dang, T. T., 2013. Analysis of microtunnelling construction operations using process simulation. Dissertation, Ruhr-Universität Bochum, Fakultät für Bau und Umweltingenieurwissenschaften, Shaker Verlag, ISBN 978-3-8440-2454-8.

2. Marzouk, M., M. Abdallah, and M. Ei-Said,, 2010. Modelling microtunnel ling projects using computer simulation. Journal of Construction Engineering and Management 136(6), 670-682,

3. Mohamed, Y. H. and R. s. Gary (2007). Delay time analysis in microtunneling projects. Journal of Construction Engineering and Management 133(2), 191-195. " '

4. Nido, A. A., C. J. Knies, and D. M. Abraham., 1999. Role of operation simulation in the analysis and improvement of microtunnelling projects. Tunneling and Underground Space Technology 14(1), 1-19.

5. Roy, Y. L. and N. Mohammad., 2007. Productivity study of microtunneling pipe installation using Simulation. Journal of Infrastructure Systems 13(3), 247-260.